Sanctuary Renovation Update Dec 2, 2021

Ceiling - Completed
天花 - 完成
Light - Completed
燈光 - 完成
Wall Painting - Completed
牆壁油漆 - 完成

Carpet - Shipping is delayed, schedule to start early January
更換地氈 - 由於貨運延誤將改於一月初開始工程
Praise the Lord!!! We identified structural issue due to previous water damage. After consulting with structural engineering, it is recommended to replace the rotten wood and strengthen the support beam. This would add one week for the renovation.
感謝神!!! 進行油漆中,發現樓宇結構由於長期漏水的緣故,木已經腐爛 . 與結構工程公司商討之後,他們建議將腐爛的木更換,並加以堅固. 工程將會延誤一星期.